Compartmentation
Where the survey stands
4 boundaries: 1 verified, 2 with open defects, 1 needing reassessment
- Defects open2
- Reassessment needed1
- Verified1
16 items on the register: 7 satisfactory, 1 repaired and accepted, 6 open defects (1 urgent), 1 could not be assessed, 1 not surveyed yet
2 things need reassessment after an alteration.
On the planBoundaries and items, floor by floor
- FD-G-01: Signed and in date, signed by a person
- FD-G-02
- FD-G-03
- FD-G-04
- FD-G-05
- FD-G-06
- FD-G-07: Not accessed
- FD-G-08
- FD-G-09
- Defects open
- Reassessment needed
- Not fully inspected
- Not surveyed
- Verified
- Satisfactory
- Defect
- Urgent defect
- Could not assess
- Not surveyed
Tap a boundary or an item to find it in the lists below. Every state is also written on the plan and in the lists.
Boundaries44 boundaries: 1 verified, 2 with open defects, 1 needing reassessment
- Reassessment needed
CF-1-01 · Compartment floor
First floor slab, between ground and first floor. Between ground floor and first floor
- Required fire resistance
- 60 min
- Design reference
- Fire strategy FS-02 rev C (fictional), drawing FS-101
- Floor
- First floor
Outstanding (2)
- CF-1-01: altered since it was surveyed, needs another look
- SP-1-02: altered since it was surveyed, needs another look
Sections
- Open-plan officeInspected
- Meeting roomInspected
- Riser cupboardInspected
- CorridorInspected
Items (4)
Add an item to CF-1-01Doors (0)
- Defects open
CW-1-01 · Compartment wall
First, server room enclosure. Between server room and corridor, archive store and tea point
- Required fire resistance
- 60 min
- Design reference
- Fire strategy FS-02 rev C (fictional), drawing FS-101
- Floor
- First floor
Remedial works: 5, 1 accepted.Handover pack for CW-1-01
Outstanding (11)
- CB-1-01: open defect
- SP-1-01: open defect
- SP-1-04: open defect
- SP-1-05: open defect
- FD-1-03: open defect on the door
- SP-1-04: rework required on the remedial work
- SP-1-01: pre-cover check not recorded yet (hold point)
- SP-1-01: open snags or actions on the remedial work
- SP-1-04: open snags or actions on the remedial work
- CB-1-01: work completed, awaiting verification
- Tea point side: partly inspected. Ceiling void above the tea point seen from one tile only.
Sections
- Server room sideInspected
- Corridor sideInspected
- Archive store sideInspected
- Tea point sidePartly inspected
Items (6)
- SP-1-01Urgent defectContractor: In progress
- LJ-1-01Satisfactory
- CB-1-01Defect, medium priorityContractor: CompletedVerification: Awaiting verification
- SP-1-03Repaired, work accepted
- SP-1-04Defect, medium priorityContractor: In progressVerification: Rework required
- SP-1-05Defect, low priorityContractor: Booked
- Verified
CW-G-01 · Compartment wall
Ground, Stair 1 enclosure. Between stair 1 and corridor and lift lobby
- Required fire resistance
- 60 min
- Design reference
- Fire strategy FS-02 rev C (fictional), drawing FS-101
- Floor
- Ground floor
Verified: nothing outstanding
Every section is inspected, every linked item is satisfactory, every linked door is signed and in date, and nothing has been altered since.
Sections
- Stair sideInspected
- Corridor sideInspected
- Lift lobby sideInspected
- Defects open
CW-G-02 · Compartment wall
Ground, service riser enclosure. Between service riser and corridor, lift lobby and wcs
- Required fire resistance
- 60 min
- Design reference
- Fire strategy FS-02 rev C (fictional), drawing FS-101
- Floor
- Ground floor
Outstanding (4)
- SP-G-02: open defect
- SP-G-03: open defect
- Inside the riser: inaccessible. Riser cupboard locked, no key on site. Key holder back Monday.
- FD-G-07: door inspection overdue
Sections
- Corridor sideInspected
- Lift lobby sideInspected
- Inside the riserInaccessible
- WC sideInspected
Register16Every item, with filters
16 items shown of 16.
SP-1-01Service penetrationUrgent defectContractor: In progressFirst, corridor, server room wall at high level
Open the record for SP-1-01First floor · in CW-1-01
Construction: Cable tray through 140 mm blockwork, about 200 by 100 mm opening
Finding: Large unsealed opening round the cable tray, about 200 by 100 mm
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SP-1-03Service penetrationRepaired, work acceptedFirst, corridor, server room wall at high level
Open the record for SP-1-03First floor · in CW-1-01
Construction: Two 15 mm copper refrigerant pipes for the server room cooling
Finding: Gap round both pipes filled with expanding foam only
Signed by Priya Nair (Level 3 passive fire protection inspection), 22 Oct 2026
Remedial work with Northgate Doorsets · accepted 24 Oct 2026
SP-G-02Service penetrationDefect, high priorityGround, corridor, riser wall at low level
Open the record for SP-G-02Ground floor · in CW-G-02
Construction: Two 110 mm plastic waste pipes through 140 mm blockwork
Finding: No collars on two 110 mm plastic pipes; open gap round both
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
Book remedial work on SP-G-02CB-1-01Cavity barrierDefect, medium priorityContractor: CompletedVerification: Awaiting verificationFirst, tea point, ceiling void on the server room line
Open the record for CB-1-01First floor · in CW-1-01
Construction: Calcium silicate board cavity barrier
Finding: Barrier board loose, gap of about 30 mm at the outside wall end
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SP-1-04Service penetrationDefect, medium priorityContractor: In progressVerification: Rework requiredFirst, archive store, server room wall at low level
Open the record for SP-1-04First floor · in CW-1-01
Construction: About 20 data cables in a 100 mm sleeve
Finding: Sleeve not sealed at either end
Signed by Priya Nair (Level 3 passive fire protection inspection), 22 Oct 2026
SP-1-05Service penetrationDefect, low priorityContractor: BookedFirst, tea point, server room wall at low level
Open the record for SP-1-05First floor · in CW-1-01
Construction: Single 20 mm data cable
Finding: Open gap of about 5 mm round the cable
Signed by Priya Nair (Level 3 passive fire protection inspection), 22 Oct 2026
SP-G-03Service penetrationDefect, low priorityGround, WCs, riser wall above the ceiling
Open the record for SP-G-03Ground floor · in CW-G-02
Construction: 100 mm steel ventilation duct, fire damper
Finding: Damper access panel missing its fixing screws
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
Book remedial work on SP-G-03CB-G-01Cavity barrierCould not assessGround, reception, ceiling void on the WC line
Open the record for CB-G-01Ground floor · not linked to a boundary
Construction: Cavity barrier as drawn on the fire strategy (not seen)
Finding: Ceiling tiles are fixed; the barrier could not be seen
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
LJ-1-01Linear jointSatisfactoryFirst, corridor, head of the server room wall
Open the record for LJ-1-01First floor · in CW-1-01
Construction: Head-of-wall joint, 15 mm, fire-rated sealant
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
LJ-1-02Linear jointSatisfactoryFirst, meeting room, slab edge at the outside wall
Open the record for LJ-1-02First floor · in CF-1-01
Construction: Slab edge seal, mineral wool and sealant
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
LJ-G-01Linear jointSatisfactoryGround, corridor, head of the Stair 1 wall
Open the record for LJ-G-01Ground floor · in CW-G-01
Construction: Head-of-wall joint, 20 mm, fire-rated sealant over mineral wool
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SF-1-01Structural fire protectionSatisfactoryFirst, open-plan office, steel beam under the roof
Open the record for SF-1-01First floor · in CF-1-01
Construction: Steel beam, board encasement, 60 minute system
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SF-G-01Structural fire protectionSatisfactoryGround, reception, steel column supporting the first floor
Open the record for SF-G-01Ground floor · in CF-1-01
Construction: Steel column, intumescent paint, 60 minute system
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SP-1-02Service penetrationSatisfactoryNeeds reassessmentFirst, riser cupboard, floor
Open the record for SP-1-02First floor · in CF-1-01
Construction: Service bundle through the slab, batt and mastic seal
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
Altered on 26 Oct 2026: New hole cored through the riser floor for a fibre cable, next to SP-1-02. Needs another look.
SP-G-01Service penetrationSatisfactoryGround, lift lobby, Stair 1 wall at high level
Open the record for SP-G-01Ground floor · in CW-G-01
Construction: Two data cables in a 25 mm sleeve, intumescent sealant
Signed by Priya Nair (Level 3 passive fire protection inspection), 21 Oct 2026
SP-G-04Service penetrationNot surveyedGround, kitchen, corridor wall (from the fire-stopping schedule)
Open the record for SP-G-04Ground floor · not linked to a boundary
Construction: Gas pipe sleeve, as scheduled
On the register from Sam Whitfield, 20 Oct 2026. Not surveyed yet.
Rooms and what was inspected236 limitations
Ground floor
- Plant roomNot surveyedOutside this survey: the landlord surveys the plant room separately.Priya Nair, 21 Oct 2026
- StoreNothing recorded
- KitchenNothing recorded
- CorridorInspectedPriya Nair, 21 Oct 2026
- Stair 1InspectedPriya Nair, 21 Oct 2026
- Lift lobbyInspectedPriya Nair, 21 Oct 2026
- LiftNothing recorded
- Service riserInaccessibleRiser cupboard locked, no key on site. Key holder back Monday.Priya Nair, 21 Oct 2026
- WCsInspectedPriya Nair, 21 Oct 2026
- ReceptionPartly inspectedCeiling void seen at two tiles only; the rest are fixed.Priya Nair, 21 Oct 2026
- Stair 2Nothing recorded
First floor
- Archive storeInspectedPriya Nair, 21 Oct 2026
- Server roomInspectedPriya Nair, 21 Oct 2026
- Tea pointPartly inspectedCeiling void above the tea point seen from one tile only.Priya Nair, 21 Oct 2026
- CorridorInspectedPriya Nair, 21 Oct 2026
- Stair 1Nothing recorded
- Lift lobbyNothing recorded
- LiftNothing recorded
- Riser cupboardInspectedPriya Nair, 21 Oct 2026
- WCsNothing recorded
- Open-plan officeInspectedPriya Nair, 21 Oct 2026
- Meeting roomInspectedPriya Nair, 21 Oct 2026
- Stair 2Nothing recorded
Alterations1Flagged for reassessment
New hole cored through the riser floor for a fibre cable, next to SP-1-02
First floor · Dan Ellis, 26 Oct 2026 · flags CF-1-01, SP-1-02 for reassessment
More information
Compartment walls and floors, service penetrations, joints, cavity barriers and structural fire protection, surveyed item by item. Doors keep their own record and are linked to the boundary they sit in.
Doors and compartmentation are recorded separately. Doorledger gives no overall result for the building.