Harbour House · handover pack · as of 27 Oct 2026
Handover: CW-1-01, First, server room enclosure
Defects open CW-1-01 is not verified: 11 things outstanding.
5 remedial works. Prices are not in this pack.
Where the works stand
- Booked
- 1
- In progress
- 1
- Awaiting verification
- 1
- Rework required
- 1
- Accepted
- 1
1 hold point waiting for a pre-cover check · 2 open snags or actions
Items and their remedial works
The contractor's completion and the verifier's decision are separate columns. Only a named verifier, never the contractor's firm, accepts.
| Item | Type | Boundary | Finding | Contractor | Target | Contractor says | Verification | Hold point | Accepted by | Show on plan |
|---|---|---|---|---|---|---|---|---|---|---|
| SP-1-01 | Service penetration | CW-1-01 | urgent: Large unsealed opening round the cable tray, about 200 by 100 mm | Northgate Doorsets | 28 Oct 2026 | In progress | Not ready for verification | Behind boxing: check not recorded | Show on plan | |
| CB-1-01 | Cavity barrier | CW-1-01 | medium: Barrier board loose, gap of about 30 mm at the outside wall end | Northgate Doorsets | 26 Oct 2026 | Completed | Awaiting verification | Above a ceiling: checked | Show on plan | |
| SP-1-03 | Service penetration | CW-1-01 | high: Gap round both pipes filled with expanding foam only | Northgate Doorsets | 23 Oct 2026 | Completed | Accepted | None | Priya Nair, Level 3 passive fire protection inspection, 24 Oct 2026 | Show on plan |
| SP-1-04 | Service penetration | CW-1-01 | medium: Sleeve not sealed at either end | Northgate Doorsets | 24 Oct 2026 | In progress | Rework required | None | Show on plan | |
| SP-1-05 | Service penetration | CW-1-01 | low: Open gap of about 5 mm round the cable | Northgate Doorsets | 3 Nov 2026 | Booked | Not ready for verification | None | Show on plan |
Specified and actual
The latest installation record for each item. Differences from the specified detail are listed in full.
| Item | Specified system | Required performance | Actual construction | Opening and services | Products | Measurements (specified / as installed) | Differences |
|---|---|---|---|---|---|---|---|
| SP-1-01 | Coated batt and ablative mastic (FS-D-02 rev B (fictional)) | EI 60 | 140 mm dense blockwork, plastered both faces | Cable tray with power and data cables; 150 x 50 mm tray in a 200 x 100 mm opening; Galvanised steel tray, PVC cables; 1 | Kestrel Fire Products (fictional) KF coated batt 50 (batch KB-0912); Kestrel Fire Products (fictional) KF ablative mastic (batch KM-3301) | Seal depth: 50 mm / 50 mm | None recorded |
| CB-1-01 | Calcium silicate cavity barrier, re-fixed (FS-D-12 (fictional)) | EI 60 | 12 mm calcium silicate board on steel angle, ceiling void above the tea point | Ceiling void on the server room line; Void 600 mm deep, 3 m long; Calcium silicate board; 0 | Kestrel Fire Products (fictional) KF barrier board 12 (batch KB-7720); Kestrel Fire Products (fictional) KF intumescent sealant (batch KS-2593) | Gap at the edges: 5 mm / 3 mm; Board or barrier thickness: 12 mm / 12 mm; Fixing centres: 300 mm / 300 mm | None recorded |
| SP-1-03 | Intumescent pipe wrap and sealant (FS-D-04 rev A (fictional)) | EI 60 | 140 mm dense blockwork, plastered both faces | Copper refrigerant pipes, lagged; 2 x 15 mm pipes in a 60 mm hole; Copper with foam lagging; 2 | Kestrel Fire Products (fictional) KF pipe wrap 25 (batch KW-2610); Kestrel Fire Products (fictional) KF intumescent sealant (batch KS-2593) | Annular gap: 15 mm / 12 mm; Seal depth: 25 mm / 25 mm; Sleeve or wrap length: 50 mm / 50 mm | None recorded |
| SP-1-04 | Cable sleeve with intumescent plugs (FS-D-09 (fictional)) | EI 60 | 140 mm dense blockwork | Data cables in a sleeve; About 20 cables in a 100 mm sleeve; PVC-sheathed copper cable; 20 | Kestrel Fire Products (fictional) KF cable plug 100 (batch KC-1180) | Seal depth: 25 mm / 18 mm; Sleeve or wrap length: 200 mm / 200 mm | Seal depth: 18 mm as installed, less than the 25 mm specified |
| SP-1-05 | Not recorded |
Photos before, during and after
Every photo is fingerprinted on the device that took it and kept with the record.
| Item | Before | During | After |
|---|---|---|---|
| SP-1-01 | m-wk-04-before | m-wk-04-during | None |
| CB-1-01 | m-wk-03-before | m-wk-03-during | m-wk-03-after |
| SP-1-03 | m-wk-01-before | m-wk-01-during | m-wk-01-after |
| SP-1-04 | m-wk-02-before | m-wk-02-during | m-wk-02-after |
| SP-1-05 | None | None | None |
Works certificates
The installer's own certificate for each item, kept as a document with its file. A certificate is evidence; it does not accept the work.
None.
Pre-cover checks
Signed by a named inspector with their competence record, with photos taken during the work, before it was covered.
| Item | Date | Result | Inspector | Competence | Note | Photos |
|---|---|---|---|---|---|---|
| CB-1-01 | 25 Oct 2026 | Ready to cover | Priya Nair | Level 3 passive fire protection inspection | Board fixed at 300 mm centres, wall end sealed, no gaps seen | m-wk-03-check |
Verification decisions
Each line is a signature: acceptance, or rework required with the reason.
| Item | Date | Decision | By | Competence | Reason |
|---|---|---|---|---|---|
| SP-1-03 | 24 Oct 2026 | Accepted | Priya Nair | Level 3 passive fire protection inspection | |
| SP-1-04 | 26 Oct 2026 | Rework required | Priya Nair | Level 3 passive fire protection inspection | Seal depth 18 mm against the 25 mm specified, and the archive side plug is not fully home. |
Snags and outstanding actions
Open ones are limitations of this handover.
| Item | Kind | What | Raised | Closed |
|---|---|---|---|---|
| SP-1-01 | Action | Agree a time with the office: the server room cooling must stay on | 27 Oct 2026, Dan Ellis | Open |
| SP-1-04 | Snag | Push the archive side plug fully home and make up the seal to 25 mm | 26 Oct 2026, Priya Nair | Open |
Remedial works on the plan
Each item's remedial work by its number on the marked plan, with its floor and position in metres from the plan's top left corner.
| No. | Item | Floor | Floor id | x (m) | y (m) | Priority | Where it stands |
|---|---|---|---|---|---|---|---|
| 1 | SP-1-01 | First floor | F1 | 9.00 | 5.00 | Urgent | In progress |
| 2 | CB-1-01 | First floor | F1 | 4.50 | 8.00 | Medium | Completed, awaiting verification |
| 3 | SP-1-03 | First floor | F1 | 9.00 | 5.20 | High | Accepted |
| 4 | SP-1-04 | First floor | F1 | 4.00 | 4.00 | Medium | Rework required |
| 5 | SP-1-05 | First floor | F1 | 6.00 | 8.00 | Low | Booked |
Marked plan
First floor: remedial works
5 items. Filled: not accepted yet. Outline: accepted by the named verifier. Shape is the finding's priority.
- Not accepted yet (filled)
- Accepted (outline)
- Urgent
- High
- 1SP-1-01 · In progress · Urgent priority
- 2CB-1-01 · Completed, awaiting verification · Medium priority
- 3SP-1-03 · Accepted · High priority
- 4SP-1-04 · Rework required · Medium priority
- 5SP-1-05 · Booked · Low priority
Limitations
- 4 of 5 works not accepted: SP-1-01 (in progress); CB-1-01 (completed, awaiting verification); SP-1-04 (rework required); SP-1-05 (booked).
- SP-1-01: hold point open, no pre-cover check recorded yet.
- SP-1-01: open action, Agree a time with the office: the server room cooling must stay on.
- SP-1-04: open snag, Push the archive side plug fully home and make up the seal to 25 mm.
- CB-1-01: no works certificate on the record.
- SP-1-03: no works certificate on the record.
- SP-1-04: differs from the specified detail. Seal depth: 18 mm as installed, less than the 25 mm specified.
- CW-1-01: CB-1-01: open defect.
- CW-1-01: SP-1-01: open defect.
- CW-1-01: SP-1-04: open defect.
- CW-1-01: SP-1-05: open defect.
- CW-1-01: FD-1-03: open defect on the door.
- CW-1-01: SP-1-04: rework required on the remedial work.
- CW-1-01: SP-1-01: pre-cover check not recorded yet (hold point).
- CW-1-01: SP-1-01: open snags or actions on the remedial work.
- CW-1-01: SP-1-04: open snags or actions on the remedial work.
- CW-1-01: CB-1-01: work completed, awaiting verification.
- CW-1-01: Tea point side: partly inspected. Ceiling void above the tea point seen from one tile only.
- Accepted means a named verifier accepted the work as recorded. Doorledger does not certify fire resistance.