Planning and reports
Large unsealed opening round the cable tray, about 200 by 100 mm
Still needed
3 still needed before it can be marked complete.
Completed is the contractor's word. Only a named verifier, never the contractor's firm, can accept the work.
In boundary CW-1-01, 60 minutes required
Intrusive work can start (Intrusive fire-stopping, works wk-seed-04). HH-RS-02 was reviewed for intrusive fire-stopping, cutting or drilling into compartment walls by Sam Whitfield (BOHS P405 Management of asbestos in buildings). Follow the restrictions below.
No asbestos found in the server room wall or its linings (samples S6 to S9). Do not open the ceiling over the open-plan office: it was not surveyed.
From HH-RS-02, reviewed by Sam Whitfield
Dated 20 Oct 2026, by Calloway Surveys Ltd (fictional)
Not covered: Server room floor void; above the suspended ceiling in the open-plan office
Not accessed: Riser cupboard (locked on the day)
Dated 15 Oct 2026, by Calloway Surveys Ltd (fictional)
Not covered: Above the suspended ceiling in the open-plan office
Will this work cut, drill or disturb the building fabric (walls, floors, ceilings, linings, frames or existing materials)?
Yes, as booked by Sam Whitfield on 22 Oct 2026
Booked as: Yes
Signed as Sam Whitfield, BOHS P405 Management of asbestos in buildings.
Kept on the record and in the audit pack.
Hold point: pre-cover check needed· Behind boxing
Hold point: this item will be covered. A competent inspector must record the pre-cover check, with photos taken during the work, before it is completed.
No differences from the specified detail in what was recorded.
| Measurement | Specified | As installed |
|---|---|---|
| Seal depth | 50 mm | 50 mm |
Recorded by Dan Ellis, 27 Oct 2026
For example EI 60
What the wall or floor is actually built of
Dan Ellis, 27 Oct 2026: Opening round the tray cleared
Dan Ellis, 27 Oct 2026: Batts in, both faces
None yet. The finished seal or barrier.
Opening the camera…
Photos are saved on this device.
No works certificate yet. The installer adds it once the installation is recorded.
The installer's certificate is kept as evidence. It does not accept the work: only the named verifier does.
Outstanding action, open: Agree a time with the office: the server room cooling must stay on · due 28 Oct 2026
Raised by Dan Ellis, 27 Oct 2026
Not completed yet